Demolition and refurbishment asbestos surveys
Intrusive asbestos surveys before demolition or a strip-out in Melbourne: when one is required, how it differs from a register and what builders need.
Before a building is demolished or substantially refurbished, the asbestos that the work is likely to disturb has to be identified and, so far as is reasonably practicable, removed. A demolition or refurbishment survey is the intrusive inspection that finds it. It goes further than a register: the surveyor opens wall cavities, lifts floor coverings and enters ceiling voids in the areas that will be disturbed.

Surveyors who take enquiries from this site work independently and agree the scope with you; this page explains the referral arrangement.
When is a demolition or refurbishment survey needed?
The Occupational Health and Safety Regulations 2017 require the person who manages or controls a workplace to identify asbestos likely to be disturbed by proposed demolition or refurbishment, then ensure it is removed: before demolition starts, or before or during a refurbishment, so far as is reasonably practicable. Before the work starts they must also review the existing register, revise it if it is inadequate for the planned work, and hand a copy to whoever is doing the job.
Houses are covered too, through a different route. When a builder or other business is engaged to demolish or refurbish domestic premises, the site becomes their workplace, and the same identify-and-remove duty falls on them. An owner in an older suburb such as Coburg or Hawthorn can commission the survey before tendering, so every builder prices the removal on the same information.
The Victorian Asbestos Hub notes two further points for demolition. The Building Act 1993 requires a building permit for demolition, and building surveyors require an asbestos survey report before issuing that permit. A planning permit may also be needed under the Planning and Environment Act 1987 where a heritage overlay or other control applies, which your council can confirm.
How it differs from a register inspection
| Register (management) survey | Demolition or refurbishment survey | |
|---|---|---|
| Purpose | Manage asbestos left in place | Find everything the works will disturb so it can come out first |
| Intrusion | Minor, with simple hand tools | Destructive: opening walls, floors, ceilings, risers |
| Standard of search | So far as is reasonably practicable | All asbestos likely to be disturbed |
| Occupancy | Building can stay in use | Area should be vacant, furniture out |
| Output | Register entries and risk ratings | Removal scope that a licensed removalist can quote on |
The national survey guide from the Asbestos and Silica Safety and Eradication Agency says that “no access” areas from earlier surveys must be accessed for a demolition survey, and that a second survey may be needed after a soft strip exposes areas that were hidden.
Where surveys find asbestos that registers missed
The national guide points to places a walk-through cannot see: wall cavities, where insulated pipes pass through masonry, suspended ceilings fixed with fibreboard tiles, partition walls made of plasterboard and fibreboard layers, rope fire seals behind trim, cement sheet packing around window and door frames, putty in old window frames, and textured coatings fixed to concrete. Plant rooms add gaskets, flues and lagging.
What the surveyor will need
- The demolition or design drawings, so the survey covers exactly the area to be disturbed.
- Vacant possession of that area, or at least furniture and stock moved out.
- Permission to make openings, and agreement on whether they will be made good afterwards.
- A builder, joiner or engineer to agree entry points where structure is involved.
- Safe access to roofs and voids, including any lifting equipment.
- The existing register and earlier clearance certificates.
What the report should give your builder
A list of every confirmed or presumed material in the work area with its location, quantity estimate, friability and condition; photos and a marked plan; the NATA endorsed laboratory results; areas that still could not be reached; and a note on whether each item needs a Class A removalist (friable material) or can be done under a Class B licence (non-friable). The national guide says the report should go to designers and contractors bidding for the work so the asbestos risk is priced and planned.
Cost
Survey prices depend on floor area, the number of openings and how many materials need samples. The Melbourne cost guide sets out sourced price ranges for sampling and reports. Budget separately for removal and for the clearance inspection that follows removal.
What a careful surveyor will refuse to do
- Survey an occupied area intrusively while staff or residents are working around it.
- Sign off a building as asbestos-free when parts of the work area were not opened.
- Rely on an old register in place of a fresh intrusive survey.
- Remove asbestos themselves under the survey contract. Removal needs a WorkSafe licence holder, and WorkSafe must be notified before most removal work starts.
Local angle
Boroondara and Maribyrnong councils both publish searchable heritage overlay information, and a heritage overlay can bring a planning permit requirement for demolition. If only part of a building may come down, the survey boundary should follow the approved demolition plan, not the whole lot, so settle the planning position before fixing the survey scope. In the CBD, a strip-out of one office floor is a refurbishment of that floor, and the register for the rest of the building still has to be reviewed against it.
What to do next
Send the drawings or a description of what is being removed, the building age and the planned start date, and ask for a demolition survey quote. WorkSafe’s guidance on demolition and refurbishment is in the Managing asbestos in workplaces compliance code, and the Victorian Asbestos Hub permits page lists the permits and notices involved.
Frequently asked questions
- Will the surveyor make holes in my walls?
Yes, that is the point of an intrusive survey. Agree in advance where openings will be made, whether a builder or engineer should approve entry points, and whether the openings will be patched or left for the demolition.
- Who pays for a demolition survey, the owner or the builder?
Whoever the contract says. At a workplace, the person who manages or controls the building must make sure the asbestos is identified; at a house, the duty sits with the builder once engaged. Many owners pay for the survey themselves so every tender is priced from one report.
- Can demolition start as soon as the asbestos is out?
Not straight away. A clearance certificate from an independent person is needed before the area is re-occupied for demolition or other work, unless the removal involved only non-friable material of 10 square metres or less.
- Can the same company survey the building and remove the asbestos?
The rules do not require the survey to be independent of the removalist, but many owners prefer a separate surveyor so the scope is not set by the firm pricing the removal. The clearance at the end is different: it must come from someone independent of the removalist and of whoever commissioned the work.